Our new Pre-school, on track for opening very soon!

Our new Pre-school, on track for opening very soon!

The interior of the Pre-school is complete.
SWW are due up this afternoon to check access for the new fresh water connection. The connection should be completed later this week.

The paths around the pre-school are being surfaced today.
The rubberised compound for the play area will be put down on Thursday.
The sewer pipe has been laid and connected but the carpark will be fenced off for the rest of the week.

Everything is on schedule for completion on Monday 29th January

Cllr David Young